Assessment Year | 2001 |
---|---|
Principal Product | double diaphragm pumps |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $50 M to 100M |
# of Employees | 235 |
Plant Area |
157,216
ft2
|
Annual Production | 84,000
pieces
|
Production Hrs. Annual | 5,161
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $316,872 | 6,688,566 |
kWh
|
$0.047 |
Electricity Demand | $150,301 | 34,456 |
kW-mo/yr
|
$4.36 |
Electricity Fees | $24,374 | - |
|
- |
Natural Gas | $12,377 | 1,484 |
MMBtu
|
$8.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $487,476 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $142,830 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,371 | $19,200 |
$8,501
85,466
kWh
|
$1,870
-
kW-mo/yr
|
- | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $5,951 | $550 |
$5,004
36,757
kWh
|
$947
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,264 | $800 |
$4,960
44,126
kWh
|
$1,304
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,982 | - |
$4,904
49,298
kWh
|
$1,078
-
kW-mo/yr
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $30,965 | $12,950 |
$24,506
217,908
kWh
|
$6,459
-
kW-mo/yr
|
- | - | |
06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $100,699 | $450 | - | - | - | $100,699 | |
07 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $8,944 | $11,800 | - | - | - | $8,944 | |
08 | 4.311: Schedule deliveries according to demand | $207,000 | $1,000 | - | - | - | $207,000 | |
09 | 4.612: Contract out maintenance | $7,300 | - | - | - | $7,300 | - | |
10 | 4.131: Modify process to reduce material use/cost | $104,000 | $24,000 | - | - | $104,000 | - | |
TOTAL RECOMMENDED | $487,476 | $70,750 |
$47,875
433,555
kWh
|
$11,658
-
kW-mo/yr
|
$111,300 | $316,643 | ||
TOTAL IMPLEMENTED | $142,830 | $56,350 |
$18,465
166,349
kWh
|
$4,121
-
kW-mo/yr
|
$111,300 | $8,944 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs