ITAC Assessment: LM0015
ITAC logo
ITAC Assessment: LM0015
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product double diaphragm pumps
NAICS
n/a
SIC 3561: Pumps and Pumping Equipment
Sales Range $50
M
to 100
M
# of Employees 235
Plant Area 157,216
ft2
Annual Production 84,000
pieces
Production Hrs. Annual 5,161
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $316,872 6,688,566
kWh
Electricity Demand $150,301 34,456
kW-mo/yr
Electricity Fees $24,374 -
Natural Gas $12,377 1,484
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $487,476 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $142,830

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $10,371 $19,200 $8,501
85,466
kWh
$1,870
-
kW-mo/yr
- -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $5,951 $550 $5,004
36,757
kWh
$947
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,264 $800 $4,960
44,126
kWh
$1,304
-
kW-mo/yr
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $5,982 - $4,904
49,298
kWh
$1,078
-
kW-mo/yr
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $30,965 $12,950 $24,506
217,908
kWh
$6,459
-
kW-mo/yr
- -
06 2.3131: Reschedule plant operations or reduce load to avoid peaks $100,699 $450 - - - $100,699
07 3.6193: Install equipment (eg compactor) to reduce disposal costs $8,944 $11,800 - - - $8,944
08 4.311: Schedule deliveries according to demand $207,000 $1,000 - - - $207,000
09 4.612: Contract out maintenance $7,300 - - - $7,300 -
10 4.131: Modify process to reduce material use/cost $104,000 $24,000 - - $104,000 -
TOTAL RECOMMENDED $487,476 $70,750 $47,875
433,555
kWh
$11,658
-
kW-mo/yr
$111,300 $316,643
TOTAL IMPLEMENTED $142,830 $56,350 $18,465
166,349
kWh
$4,121
-
kW-mo/yr
$111,300 $8,944
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs