ITAC Assessment: LL0336
ITAC logo
ITAC Assessment: LL0336
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Daily Newspaper
NAICS 511110: Newspaper Publishers
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $1
M
to 5
M
# of Employees 150
Plant Area 63,400
ft2
Annual Production 150,000
pieces
Production Hrs. Annual 8,320
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $328,364 4,281,800
kWh
Natural Gas $1,925 141
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,565 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,893

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $26,938 $6,840 $26,938
351,258
kWh
- -
02 4.611: Begin a practice of predictive / preventative maintenance $15,990 $5,455 - $15,990 -
03 2.7111: Reduce illumination to minimum necessary levels $4,848 $1,290 $4,848
63,221
kWh
- -
04 4.611: Begin a practice of predictive / preventative maintenance $3,008 $630 $2,508
32,708
kWh
- $500
05 2.7135: Install occupancy sensors $1,947 $2,100 $1,947
25,382
kWh
- -
06 2.6211: Conserve energy by efficient use of vending machines $1,072 $1,336 $1,072
13,978
kWh
- -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $392 $245 $179
2,330
kWh
$213 -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $370 $127 $370
4,827
kWh
- -
TOTAL RECOMMENDED $54,565 $18,023 $37,862
493,704
kWh
$16,203 $500
TOTAL IMPLEMENTED $31,893 $9,570 $31,393
409,348
kWh
- $500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs