| Assessment Year | 2006 |
|---|---|
| Principal Product | Rice drying |
| NAICS | 311212: Rice Milling |
| SIC | 2044: Rice Milling |
| Sales Range | $1 M to 5M |
| # of Employees | 4 |
| Plant Area |
30,000
ft2
|
| Annual Production | 214,000
bbl
|
| Production Hrs. Annual | 3,640
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $27,134 | 348,341 |
kWh
|
$0.078 |
| Electricity Demand | $7,961 | 1,678 |
kW-mo/yr
|
$4.74 |
| Electricity Fees | $3,340 | - |
|
- |
| Natural Gas | $52,425 | 4,777 |
MMBtu
|
$10.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $7,118 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,113 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,342 | $2,748 |
$3,052
39,172
kWh
|
$290 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,136 | $1,373 |
$1,951
25,050
kWh
|
$185 | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $570 | $151 | - | - |
$570
-
MMBtu
|
|
| 04 | 2.7134: Use photocell controls | $527 | $150 |
$481
6,180
kWh
|
$46 | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $333 | $60 |
$304
3,896
kWh
|
$29 | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $210 | $120 |
$192
2,471
kWh
|
$18 | - | |
| TOTAL RECOMMENDED | $7,118 | $4,602 |
$5,980
76,769
kWh
|
$568 |
$570
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,113 | $331 |
$496
6,367
kWh
|
$47 |
$570
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs