Assessment Year | 2006 |
---|---|
Principal Product | HF and Genetron |
NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
625,000
ft2
|
Annual Production | 163,000
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $8,226,184 | 153,691,694 |
kWh
|
$0.054 |
Electricity Demand | $2,465,328 | 240,373 |
kW-mo/yr
|
$10.26 |
Natural Gas | $17,911,478 | 2,010,024 |
MMBtu
|
$8.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,309,584 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,715,248 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $3,334,582 | $60,000 | - | - |
$3,334,582
-
MMBtu
|
- | |
02 | 2.3412: Use waste heat to produce steam to drive a steam turbine-generator | $2,369,946 | $5,024,000 |
$4,688,352
87,600,000
kWh
|
$1,231,200
-
kW-mo/yr
|
$(-3,549,606.0)
-
MMBtu
|
- | |
03 | 2.2135: Repair and eliminate steam leaks | $323,360 | $14,100 | - | - |
$323,360
-
MMBtu
|
- | |
04 | 2.2511: Insulate bare equipment | $185,638 | $4,644 | - | - |
$185,638
-
MMBtu
|
- | |
05 | 2.7134: Use photocell controls | $45,203 | $6,300 |
$45,203
844,595
kWh
|
- | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $32,924 | $11,000 |
$32,924
615,165
kWh
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $12,103 | $1,218 | - | - |
$12,103
-
MMBtu
|
- | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,818 | $3,500 |
$1,782
33,288
kWh
|
- | - | $3,036 | |
09 | 2.7135: Install occupancy sensors | $1,010 | $2,813 |
$1,010
18,865
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $6,309,584 | $5,127,575 |
$4,769,271
89,111,913
kWh
|
$1,231,200
-
kW-mo/yr
|
$306,077
-
MMBtu
|
$3,036 | ||
TOTAL IMPLEMENTED | $3,715,248 | $81,618 |
$45,203
844,595
kWh
|
- |
$3,670,045
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs