Assessment Year | 2005 |
---|---|
Principal Product | Rice Drying |
NAICS | 311212: Rice Milling |
SIC | 2044: Rice Milling |
Sales Range | $500 k to 1M |
# of Employees | 11 |
Plant Area |
25,000
ft2
|
Annual Production | 10,816,000
lb
|
Production Hrs. Annual | 3,984
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $47,800 | 444,570 |
kWh
|
$0.11 |
Electricity Demand | $9,800 | 2,467 |
kW-mo/yr
|
$3.97 |
Electricity Fees | $2,189 | - |
|
- |
Natural Gas | $38,387 | 6,701 |
MMBtu
|
$5.73 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,994 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,228 | $1,600 |
$6,000
55,802
kWh
|
- | $228 | - | - | - | |
02 | 2.2511: Insulate bare equipment | $6,074 | - | - | - | - |
$6,074
-
MMBtu
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,146 | $700 |
$993
9,238
kWh
|
$111
-
kW-mo/yr
|
$42 | - | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $745 | $300 | - | - | - |
$745
-
MMBtu
|
- | - | |
05 | 2.7134: Use photocell controls | $464 | - |
$447
4,156
kWh
|
- | $17 | - | - | - | |
06 | 2.7135: Install occupancy sensors | $62 | - |
$60
560
kWh
|
- | $2 | - | - | - | |
07 | 4.611: Begin a practice of predictive / preventative maintenance | $3,875 | $350 | - | - | - | - | $1,375 | $2,500 | |
TOTAL RECOMMENDED | $18,594 | $2,950 |
$7,500
69,756
kWh
|
$111
-
kW-mo/yr
|
$289 |
$6,819
-
MMBtu
|
$1,375 | $2,500 | ||
TOTAL IMPLEMENTED | $11,994 | $2,950 |
$6,993
65,040
kWh
|
$111
-
kW-mo/yr
|
$270 |
$745
-
MMBtu
|
$1,375 | $2,500 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs