ITAC Assessment: LL0219
ITAC logo
ITAC Assessment: LL0219
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Oilfield Equipment
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area 225,000
ft2
Annual Production 6,000
pieces
Production Hrs. Annual 5,824
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $333,249 7,193,129
kWh
Electricity Demand $115,777 14,402
kW-mo/yr
Electricity Fees $17,097 -
Natural Gas $164,004 17,693
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $338,316 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $312,447

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
01 2.4324: Replace hydraulic / pneumatic equipment with electric equipment $49,904 $26,850 $48,077
1,037,703
kWh
- $1,827 - - - -
02 2.7232: Replace existing hvac unit with high efficiency model $38,931 $18,717 - - - $38,931
-
MMBtu
- - -
03 2.7243: Improve air circulation with destratification fans / other methods $18,345 $4,495 $17,673
385,731
kWh
- $672 - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $10,142 $60 $9,771
210,896
kWh
- $371 - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,865 $3,360 $8,540
184,324
kWh
- $325 - - - -
06 2.7111: Reduce illumination to minimum necessary levels $7,000 $465 $5,539
119,549
kWh
$1,205
-
kW-mo/yr
$256 - - - -
07 2.2511: Insulate bare equipment $1,372 $570 - - - $1,372
-
MMBtu
- - -
08 2.7134: Use photocell controls $1,919 $180 $1,849
39,911
kWh
- $70 - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $2,270 $1,581 $1,702
36,734
kWh
$485
-
kW-mo/yr
$83 - - - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $695 $525 $231
4,993
kWh
- $9 - - $455 -
11 2.7135: Install occupancy sensors $524 $90 $505
10,909
kWh
- $19 - - - -
12 3.5311: Recover and reuse waste material $11,259 $18,500 - - - - $4,239
-
gal
$7,020 -
13 4.611: Begin a practice of predictive / preventative maintenance $184,840 $1,190 - - - - - $180,840 $4,000
14 4.611: Begin a practice of predictive / preventative maintenance $2,250 $1,486 - - - - - $2,250 -
TOTAL RECOMMENDED $338,316 $78,069 $93,887
2,030,750
kWh
$1,690
-
kW-mo/yr
$3,632 $40,303
-
MMBtu
$4,239
-
gal
$190,565 $4,000
TOTAL IMPLEMENTED $312,447 $73,019 $70,170
1,514,561
kWh
$485
-
kW-mo/yr
$2,685 $40,303
-
MMBtu
$4,239
-
gal
$190,565 $4,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Personnel Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs