| Assessment Year | 2001 |
|---|---|
| Principal Product | Oil/Gas Platforms and Instrumentation Panels |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 450 |
| Plant Area |
1,726,618
ft2
|
| Annual Production | 8,500
ton
|
| Production Hrs. Annual | 3,000
hrs
|
| Location (State) | Louisiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $153,552 | 2,065,551 |
kWh
|
$0.074 |
| Electricity Demand | $40,189 | 7,231 |
kW-mo/yr
|
$5.56 |
| Electricity Fees | $(-24,830.0) | - |
|
- |
| Natural Gas | $1,177 | 216 |
MMBtu
|
$5.45 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,897 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,557 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Water Disposal Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.8123: Pay utility bills on time | $268 | - | - | $268 | - | - | |
| 02 | 2.8112: Combine utility meters | $2,400 | - | - | $2,400 | - | - | |
| 03 | 2.8112: Combine utility meters | $240 | - | - | - | - |
$240
-
Tgal
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,889 | $300 |
$2,778
55,821
kWh
|
$111 | - | - | |
| 05 | 2.8114: Change rate schedules or other changes in utility service | $5,100 | - | - | - |
$5,100
-
Tgal
|
- | |
| TOTAL RECOMMENDED | $10,897 | $300 |
$2,778
55,821
kWh
|
$2,779 |
$5,100
-
Tgal
|
$240
-
Tgal
|
||
| TOTAL IMPLEMENTED | $5,557 | $300 |
$2,778
55,821
kWh
|
$2,779 | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs