ITAC Assessment: LL0108
ITAC logo
ITAC Assessment: LL0108
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Oil/Gas Platforms and Instrumentation Panels
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 1,726,618
ft2
Annual Production 8,500
ton
Production Hrs. Annual 3,000
hrs
Location (State) Louisiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,552 2,065,551
kWh
Electricity Demand $40,189 7,231
kW-mo/yr
Electricity Fees $(-24,830.0) -
Natural Gas $1,177 216
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,897 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,557

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Water Disposal Savings Water Consumption Savings
01 2.8123: Pay utility bills on time $268 - - $268 - -
02 2.8112: Combine utility meters $2,400 - - $2,400 - -
03 2.8112: Combine utility meters $240 - - - - $240
-
Tgal
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,889 $300 $2,778
55,821
kWh
$111 - -
05 2.8114: Change rate schedules or other changes in utility service $5,100 - - - $5,100
-
Tgal
-
TOTAL RECOMMENDED $10,897 $300 $2,778
55,821
kWh
$2,779 $5,100
-
Tgal
$240
-
Tgal
TOTAL IMPLEMENTED $5,557 $300 $2,778
55,821
kWh
$2,779 - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs