| Assessment Year | 2026 |
|---|---|
| Principal Product | Precision Metal Components |
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
60,000
ft2
|
| Annual Production | 700,000
pieces
|
| Production Hrs. Annual | 4,576
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $112,485 | 1,037,389 |
kWh
|
$0.11 | |
| Electricity Demand | $23,714 | 4,304 |
kW-mo/yr
|
$5.51 | |
| Electricity Fees | $5,147 | - |
|
- | |
| Natural Gas | $10,220 | 2,431 |
MMBtu
|
$4.20 | |
| Waste Disposal Costs | |||||
| Water Usage | $33,904 | 2,346 |
Tgal
|
$14.45 | |
| Water Disposal | $21,506 | 2,340 |
Tgal
|
$9.19 | |
| TOTAL YEARLY COSTS | $206,976 | ||||
| RECOMMENDED SAVINGS* | $53,306 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,477 | $1,318 |
$1,301
12,044
kWh
|
$176
-
kW-mo/yr
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,171 | $1,000 |
$1,099
10,175
kWh
|
$72
-
kW-mo/yr
|
- | - | |
| 03 | 4.651: Install back-up equipment | $28,409 | $40,000 | - | - | - | $28,409 | |
| 04 | 2.2443: Re-use or recycle hot or cold process exhaust air | $2,218 | $4,000 | - | - |
$2,218
-
MMBtu
|
- | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,009 | $2,000 |
$943
8,736
kWh
|
$66
-
kW-mo/yr
|
- | - | |
| 06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,180 | $6,564 |
$1,921
17,789
kWh
|
$259
-
kW-mo/yr
|
- | - | |
| 07 | 2.7232: Replace existing hvac unit with high efficiency model | $13,065 | $57,445 |
$6,750
62,496
kWh
|
$331
-
kW-mo/yr
|
- | $5,984 | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,777 | $18,000 |
$3,529
32,675
kWh
|
$248
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $53,306 | $130,327 |
$15,543
143,915
kWh
|
$1,152
-
kW-mo/yr
|
$2,218
-
MMBtu
|
$34,393 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs