Assessment Year | 2024 |
---|---|
Principal Product | Sewage Treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $5 M to 10M |
# of Employees | 80 |
Plant Area |
1,200,000
ft2
|
Annual Production | 10,220,000
Tgal
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | New Jersey |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,439,996 | 16,753,526 |
kWh
|
$0.086 |
Electricity Demand | $141,414 | 33,494 |
kW-mo/yr
|
$4.22 |
Electricity Fees | $48,000 | - |
|
- |
Natural Gas | $1,158,864 | 392,327 |
MMBtu
|
$2.95 |
TOTAL YEARLY COSTS | $2,788,274 | |||
RECOMMENDED SAVINGS* | $400,307 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $49,885 | $128,000 |
$47,332
550,368
kWh
|
$2,553
-
kW-mo/yr
|
|
02 | 2.4112: Install soft-start to eliminate nuisance trips | $41,677 | $125,540 | - |
$41,677
-
kW-mo/yr
|
|
03 | 2.4322: Use or replace with energy efficient substitutes | $308,745 | $1,680,000 |
$289,249
3,363,360
kWh
|
$19,496
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $400,307 | $1,933,540 |
$336,581
3,913,728
kWh
|
$63,726
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs