ITAC Assessment: LE0220
ITAC logo
ITAC Assessment: LE0220
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Commercial entrances, windows, and storefront systems
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $5
M
to 10
M
# of Employees 49
Plant Area 88,000
ft2
Annual Production 7,000
pieces
Production Hrs. Annual 2,080
hrs
Location (State) New Jersey

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,296 412,613
kWh
Electricity Demand $11,683 1,863
kW-mo/yr
Natural Gas $73,307 6,998
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,519 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,767

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7231: Use radiant heater for spot heating $13,454 $18,500 - - $13,454
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $7,586 $500 $5,411
60,120
kWh
$2,175
-
kW-mo/yr
-
03 2.2511: Insulate bare equipment $594 $450 $449
4,990
kWh
$145
-
kW-mo/yr
-
04 2.4231: Reduce the pressure of compressed air to the minimum required $377 $80 $258
2,871
kWh
$119
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $298 $450 $298
3,309
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $3,210 $25,315 $2,281
25,339
kWh
$929
-
kW-mo/yr
-
TOTAL RECOMMENDED $25,519 $45,295 $8,697
96,629
kWh
$3,368
-
kW-mo/yr
$13,454
-
MMBtu
TOTAL IMPLEMENTED $11,767 $26,345 $8,399
93,320
kWh
$3,368
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs