Assessment Year | 2004 |
---|---|
Principal Product | Injection Molded Medical Components |
NAICS | 339113: Surgical Appliance and Supplies Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 160 |
Plant Area |
60,000
ft2
|
Annual Production | 90,000,000
pieces
|
Production Hrs. Annual | 5,616
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $408,259 | 6,081,000 |
kWh
|
$0.067 |
Electricity Demand | $85,116 | 14,819 |
kW-mo/yr
|
$5.74 |
Natural Gas | $16,928 | 2,134 |
MMBtu
|
$7.93 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,938 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,536 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $34,823 | $36,750 |
$34,823
429,387
kWh
|
- | - | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,610 | $3,000 | - |
$8,610
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,713 | $3,840 |
$4,963
61,198
kWh
|
$750
-
kW-mo/yr
|
- | |
04 | 2.3212: Optimize plant power factor | $3,600 | $5,000 | - | - | $3,600 | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,466 | $3,000 |
$2,142
26,414
kWh
|
$324
-
kW-mo/yr
|
- | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,461 | - |
$1,461
18,040
kWh
|
- | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,401 | $500 |
$1,251
15,448
kWh
|
$150
-
kW-mo/yr
|
- | |
08 | 2.2625: Chill water to the highest temperature possible | $864 | - |
$864
10,670
kWh
|
- | - | |
TOTAL RECOMMENDED | $58,938 | $52,090 |
$45,504
561,157
kWh
|
$9,834
-
kW-mo/yr
|
$3,600 | ||
TOTAL IMPLEMENTED | $40,536 | $40,590 |
$39,786
490,585
kWh
|
$750
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs