Assessment Year | 1993 |
---|---|
Principal Product | Industrial Vehicles |
NAICS |
n/a
|
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
600,000
ft2
|
Annual Production | 16,000
pieces
|
Production Hrs. Annual | 4,420
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $372,403 | 8,957,210 |
kWh
|
$0.042 |
Natural Gas | $198,160 | 42,474 |
MMBtu
|
$4.67 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,618 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,003 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,619 | $53,048 |
$6,619
159,144
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $122 | $480 |
$122
2,931
kWh
|
- | - | |
03 | 3.4114: Replace city water with recycled water via cooling tower | $12,010 | $17,000 |
$(-683.0)
(-16,413)
kWh
|
- | $12,693 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,454 | $190 |
$1,454
29,015
kWh
|
- | - | |
05 | 3.4115: Recover and reuse cooling water | $11,879 | $200 | - | - | $11,879 | |
06 | 2.2437: Recover waste heat from equipment | $6,463 | $8,750 | - |
$6,463
-
MMBtu
|
- | |
07 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $5,133 | $20,000 |
$7,669
123,681
kWh
|
$(-2,536.0)
-
MMBtu
|
- | |
08 | 2.3191: Use demand controller or load shedder | $1,964 | $6,000 |
$1,964
-
kWh
|
- | - | |
09 | 2.4314: Use synthetic lubricant | $1,426 | - |
$1,426
34,291
kWh
|
- | - | |
10 | 2.4133: Use most efficient type of electric motors | $548 | $946 |
$548
13,189
kWh
|
- | - | |
TOTAL RECOMMENDED | $47,618 | $106,614 |
$19,119
345,838
kWh
|
$3,927
-
MMBtu
|
$24,572 | ||
TOTAL IMPLEMENTED | $14,003 | $1,816 |
$2,124
45,135
kWh
|
- | $11,879 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs