ITAC Assessment: KU0255
ITAC logo
ITAC Assessment: KU0255
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product EGG PROCESSING EQUIPMENT
NAICS
n/a
SIC 3556: Food Products Machinery
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 50
pieces
Production Hrs. Annual 2,520
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,735 473,916
kWh
Natural Gas $5,513 1,438
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,878 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,120

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,435 $4,907 $2,435
40,152
kWh
- -
02 2.8121: Apply for tax-free status for energy purchases $646 - $646
-
kWh
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $107 $40 $107
1,758
kWh
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $213 $100 $213
3,517
kWh
- -
05 2.1233: Analyze flue gas for proper air/fuel ratio $154 - - $234
-
MMBtu
$(-80.0)
06 2.1123: Install automatic stack damper $323 $600 - $323
-
MMBtu
-
TOTAL RECOMMENDED $3,878 $5,647 $3,401
45,427
kWh
$557
-
MMBtu
$(-80.0)
TOTAL IMPLEMENTED $1,120 $140 $966
5,275
kWh
$234
-
MMBtu
$(-80.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs