ITAC Assessment: KU0101
ITAC logo
ITAC Assessment: KU0101
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product PATCHES AND ENBLEMS
NAICS
n/a
SIC 2395: Pleating, Decorative and Novelty Stitching, and Tucking for the Trade
Sales Range $1
M
to 5
M
# of Employees 55
Plant Area
n/a
Annual Production 3,000,000
pieces
Production Hrs. Annual 2,250
hrs
Location (State) Kansas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $12,704 163,540
kWh
Natural Gas $3,328 651
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,948 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,002 $600 $1,002
12,896
kWh
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $199 $300 - $199
-
MMBtu
03 2.1123: Install automatic stack damper $230 $750 - $230
-
MMBtu
04 2.6214: Shut off pilots in standby equipment $107 - - $107
-
MMBtu
05 2.6121: Reduce hot water temperature to the minimum required $410 - $410
5,275
kWh
-
TOTAL RECOMMENDED $1,948 $1,650 $1,412
18,171
kWh
$536
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs