ITAC Assessment: IP0165
ITAC logo
ITAC Assessment: IP0165
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Disassemble/sort and repackage construction waste lumber and concrete products
NAICS 321999: All Other Miscellaneous Wood Product Manufacturing
SIC 2499: Wood Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 30
Plant Area 108,000
ft2
Annual Production 78,000
ton
Production Hrs. Annual 2,860
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $28,788 446,640
kWh
Electricity Demand $83,239 3,881
kW-mo/yr
Electricity Fees $18,491 -
Natural Gas $1,489 187
MMBtu
TOTAL YEARLY COSTS $132,007
RECOMMENDED SAVINGS* $7,790 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4239: Eliminate or reduce compressed air usage $693 - $289
4,487
kWh
$404
-
kW-mo/yr
- -
02 2.7221: Lower temperature during the winter season and vice-versa $533 $23 $431
6,689
kWh
- - $102
-
MMBtu
03 2.3212: Optimize plant power factor $6,564 $11,200 - - $6,564 -
TOTAL RECOMMENDED $7,790 $11,223 $720
11,176
kWh
$404
-
kW-mo/yr
$6,564 $102
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs