| Assessment Year | 2022 |
|---|---|
| Principal Product | steering components |
| NAICS | 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $100 M to 500M |
| # of Employees | 360 |
| Plant Area |
224,000
ft2
|
| Annual Production | 917,500
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Indiana |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $445,543 | 8,215,339 |
kWh
|
$0.054 | |
| Electricity Demand | $234,719 | 15,636 |
kW-mo/yr
|
$15.01 | |
| Natural Gas | $123,608 | 47,181 |
MMBtu
|
$2.62 | |
| Waste Disposal Costs | |||||
| Water Usage | $27,656 | 11,906 |
Tgal
|
$2.32 | |
| TOTAL YEARLY COSTS | $831,526 | ||||
| RECOMMENDED SAVINGS* | $56,801 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $56,801 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7224: Reduce space conditioning during non-working hours | $759 | $18 |
$357
6,589
kWh
|
- |
$402
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,626 | $271 |
$6,423
118,510
kWh
|
$203
-
kW-mo/yr
|
- | |
| 03 | 2.7135: Install occupancy sensors | $2,159 | $767 |
$2,159
39,835
kWh
|
- | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $20,612 | $34,884 |
$19,981
368,647
kWh
|
$632
-
kW-mo/yr
|
- | |
| 05 | 2.1224: Replace boiler | $26,645 | $57,558 | - | - |
$26,645
-
MMBtu
|
|
| TOTAL RECOMMENDED | $56,801 | $93,497 |
$28,920
533,581
kWh
|
$835
-
kW-mo/yr
|
$27,047
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $56,801 | $93,497 |
$28,920
533,581
kWh
|
$835
-
kW-mo/yr
|
$27,047
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs