ITAC Assessment: IP0129
ITAC logo
ITAC Assessment: IP0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Machine Parts
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 16
Plant Area 28,500
ft2
Annual Production 140,000
units
Production Hrs. Annual 2,470
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,850 300,640
kWh
Electricity Fees $222 -
Natural Gas $5,651 832
MMBtu
TOTAL YEARLY COSTS $36,723
RECOMMENDED SAVINGS* $2,363 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,363

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $213 $5 $213
2,079
kWh
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,369 $210 $1,369
13,339
kWh
03 2.4231: Reduce the pressure of compressed air to the minimum required $148 $125 $148
1,436
kWh
04 2.7135: Install occupancy sensors $633 $1,137 $633
6,168
kWh
TOTAL RECOMMENDED $2,363 $1,477 $2,363
23,022
kWh
TOTAL IMPLEMENTED $2,363 $1,477 $2,363
23,022
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs