ITAC Assessment: IC0259
ITAC logo
ITAC Assessment: IC0259
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Solder Wire, Preform, and Bar Solder
NAICS 331491: Nonferrous Metal (except Copper and Aluminum) Rolling, Drawing, and Extruding
SIC 3356: Rolling, Drawing, and Extruding of Nonferrous Metals, Except Copper and Aluminum
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 58,000
ft2
Annual Production 1,785,594
lb
Production Hrs. Annual 3,960
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $54,505 973,218
kWh
Electricity Demand $15,926 2,159
kW-mo/yr
Natural Gas $30,601 5,276
MMBtu
TOTAL YEARLY COSTS $101,032
RECOMMENDED SAVINGS* $23,764 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $914 $50 $653
11,666
kWh
$261
-
kW-mo/yr
02 2.4239: Eliminate or reduce compressed air usage $9,350 $730 $9,350
119,271
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $10,107 $15,295 $7,226
129,103
kWh
$2,882
-
kW-mo/yr
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,393 $953 $2,383
42,198
kWh
$1,010
-
kW-mo/yr
TOTAL RECOMMENDED $23,764 $17,028 $19,612
302,238
kWh
$4,152
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs