ITAC Assessment: IC0202
ITAC logo
ITAC Assessment: IC0202
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Wastewater Treatment Facility
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 4
Plant Area 885,174
ft2
Annual Production 2,737,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $322,214 3,465,396
kWh
Natural Gas $42,221 8,788
MMBtu
TOTAL YEARLY COSTS $364,435
RECOMMENDED SAVINGS* $113,916 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $105,484

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4133: Use most efficient type of electric motors $86,346 $283,248 $86,346
959,402
kWh
02 2.7142: Utilize higher efficiency lamps and/or ballasts $9,269 $14,085 $9,269
102,984
kWh
03 2.7142: Utilize higher efficiency lamps and/or ballasts $9,869 $16,625 $9,869
93,075
kWh
04 2.4133: Use most efficient type of electric motors $8,432 $34,164 $8,432
80,928
kWh
TOTAL RECOMMENDED $113,916 $348,122 $113,916
1,236,389
kWh
TOTAL IMPLEMENTED $105,484 $313,958 $105,484
1,155,461
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs