Assessment Year | 2017 |
---|---|
Principal Product | Lead Chemicals |
NAICS | 331410: Nonferrous Metal (except Aluminum) Smelting and Refining |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
73,400
ft2
|
Annual Production | 76,000
units
|
Production Hrs. Annual | 8,600
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $922,541 | 12,473,333 |
kWh
|
$0.074 |
Electricity Demand | $293,505 | 23,609 |
kW-mo/yr
|
$12.43 |
Electricity Fees | $1,216,046 | - |
|
- |
Natural Gas | $281,326 | 72,857 |
MMBtu
|
$3.86 |
TOTAL YEARLY COSTS | $2,713,418 | |||
RECOMMENDED SAVINGS* | $199,566 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $124,178 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $90,126 | $26,155 | - |
$90,126
-
kW-mo/yr
|
- | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $56,000 | $64,000 | - | - |
$56,000
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $23,650 | $4,800 |
$23,650
315,334
kWh
|
- | - | |
04 | 2.4131: Size electric motors for peak operating efficiency | $10,402 | $8,241 |
$10,402
135,912
kWh
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $8,986 | $2,550 | - | - |
$8,986
-
MMBtu
|
|
06 | 2.4133: Use most efficient type of electric motors | $10,402 | $12,724 |
$10,402
135,912
kWh
|
- | - | |
TOTAL RECOMMENDED | $199,566 | $118,470 |
$44,454
587,158
kWh
|
$90,126
-
kW-mo/yr
|
$64,986
-
MMBtu
|
||
TOTAL IMPLEMENTED | $124,178 | $39,196 |
$34,052
451,246
kWh
|
$90,126
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs