| Assessment Year | 2005 |
|---|---|
| Principal Product | Fruit Juice and Sauce |
| NAICS | 311421: Fruit and Vegetable Canning |
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $10 M to 50M |
| # of Employees | 265 |
| Plant Area |
404,209
ft2
|
| Annual Production | 50,000,000
lb
|
| Production Hrs. Annual | 8,496
hrs
|
| Location (State) | Wisconsin |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $775,048 | 23,637,148 |
kWh
|
$0.033 |
| Electricity Demand | $439,035 | 44,397 |
kW-mo/yr
|
$9.89 |
| Electricity Fees | $7,690 | - |
|
- |
| Natural Gas | $1,433,206 | 205,858 |
MMBtu
|
$6.96 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $279,841 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $192,777 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1392: Replace purchased steam with other energy source | $106,617 | $213,420 | - | - |
$106,012
-
MMBtu
|
- | - |
$605
-
Tgal
|
|
| 02 | 2.2191: Substitute hot process fluids for steam | $79,621 | $634,572 | - | - |
$74,621
-
MMBtu
|
- | - |
$5,000
-
Tgal
|
|
| 03 | 2.2113: Repair or replace steam traps | $29,831 | $1,638 | - | - |
$29,232
-
MMBtu
|
- | - |
$599
-
Tgal
|
|
| 04 | 2.2135: Repair and eliminate steam leaks | $6,051 | $400 | - | - |
$5,689
-
MMBtu
|
- | - |
$362
-
Tgal
|
|
| 05 | 2.1116: Improve combustion control capability | $13,789 | $3,500 | - | - |
$13,789
-
MMBtu
|
- | - | - | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,956 | - | - | - |
$4,956
-
MMBtu
|
- | - | - | |
| 07 | 2.2621: Modify refrigeration system to operate at a lower pressure | $7,443 | $15,000 |
$5,249
159,055
kWh
|
$2,194
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 2.3212: Optimize plant power factor | $13,904 | $70,000 | - |
$13,904
-
kW-mo/yr
|
- | - | - | - | |
| 09 | 2.4133: Use most efficient type of electric motors | $17,156 | $81,881 |
$11,489
348,192
kWh
|
$5,667
-
kW-mo/yr
|
- | - | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $473 | $3,388 |
$211
6,401
kWh
|
$156
-
kW-mo/yr
|
- | $19 | $87 | - | |
| TOTAL RECOMMENDED | $279,841 | $1,023,799 |
$16,949
513,648
kWh
|
$21,921
-
kW-mo/yr
|
$234,299
-
MMBtu
|
$19 | $87 |
$6,566
-
Tgal
|
||
| TOTAL IMPLEMENTED | $192,777 | $374,227 |
$11,700
354,593
kWh
|
$19,727
-
kW-mo/yr
|
$159,678
-
MMBtu
|
$19 | $87 |
$1,566
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs