ITAC Assessment: IC0040
ITAC logo
ITAC Assessment: IC0040
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Extruded Aluminum Parts
NAICS
n/a
SIC 3354: Aluminum Extruded Products
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 155,000
ft2
Annual Production 30,797,532
lb
Production Hrs. Annual 7,038
hrs
Location (State) Indiana

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $574,016 10,972,000
kWh
Electricity Demand $229,538 22,861
kW-mo/yr
Natural Gas $444,664 63,257
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $374,027 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $203,980

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $15,248 $47,200 $12,060
268,007
kWh
$4,511
-
kW-mo/yr
- - $(-929.0) - $(-394.0) -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,379 $23,767 $5,385
119,668
kWh
$1,998
-
kW-mo/yr
- - $314 - $682 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $13,978 $3,100 $10,174
226,080
kWh
$3,804
-
kW-mo/yr
- - - - - -
04 2.4239: Eliminate or reduce compressed air usage $1,817 - $1,323
29,402
kWh
$494
-
kW-mo/yr
- - - - - -
05 2.6218: Turn off equipment when not in use $5,341 - $3,848
85,512
kWh
$1,493
-
kW-mo/yr
- - - - - -
06 2.6218: Turn off equipment when not in use $3,923 $5,500 $2,581
57,352
kWh
$1,342
-
kW-mo/yr
- - - - - -
07 2.1133: Adjust burners for efficient operation $10,651 $2,640 - - $10,651
-
MMBtu
- - - - -
08 2.2514: Cover open tanks $18,222 $3,181 - - $18,222
-
MMBtu
- - - - -
09 2.2511: Insulate bare equipment $1,281 $756 - - $1,281
-
MMBtu
- - - - -
10 2.2511: Insulate bare equipment $2,271 $7,328 - - $2,271
-
MMBtu
- - - - -
11 2.2511: Insulate bare equipment $10,938 $7,035 - - $10,938
-
MMBtu
- - - - -
12 2.2511: Insulate bare equipment $2,981 $2,477 - - $2,981
-
MMBtu
- - - - -
13 2.2414: Use waste heat from hot flue gases to preheat $3,761 $8,173 - - $3,761
-
MMBtu
- - - - -
14 2.2135: Repair and eliminate steam leaks $471 $225 - - $471
-
MMBtu
- - - - -
15 3.1242: Allow drainage before withdrawing object $10,813 - - - - - - - $10,813 -
16 3.7197: Use ultrasonic cleaning $21,427 $33,000 - - - $4,800
-
lb
- - $16,536 $91
-
Tgal
17 3.7224: Use pumps and piping to decrease the frequency of spillage during material transfer $81,120 $370,000 - - - - - - $81,120 -
18 4.447: Automate payroll system $97,419 $9,377 - - - - $35,301 $62,118 - -
19 4.426: Modify workload $63,986 $46,300 - - - - - $63,986 - -
TOTAL RECOMMENDED $374,027 $570,059 $35,371
786,021
kWh
$13,642
-
kW-mo/yr
$50,576
-
MMBtu
$4,800
-
lb
$34,686 $126,104 $108,757 $91
-
Tgal
TOTAL IMPLEMENTED $203,980 $398,007 $14,078
312,834
kWh
$5,640
-
kW-mo/yr
$5,723
-
MMBtu
- $35,301 $62,118 $81,120 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs