ITAC Assessment: IA0474
ITAC logo
ITAC Assessment: IA0474
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Automotive Differential Gears
NAICS 811113: Automotive Transmission Repair
SIC 7537: Automotive Transmission Repair Shops
Sales Range $10
M
to 50
M
# of Employees 57
Plant Area 105,000
ft2
Annual Production 4,230,000
pieces
Production Hrs. Annual 7,200
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $307,490 7,588,000
kWh
Electricity Demand $98,197 14,016
kW-mo/yr
Natural Gas $195,836 36,947
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,023 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,989 $668 $3,872
95,616
kWh
$1,117
-
kW-mo/yr
-
02 2.7491: Insulate glazing, walls, ceilings, and roofs $2,851 $5,045 - - $2,851
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,183 $11,760 $1,662
41,040
kWh
$1,521
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,023 $17,473 $5,534
136,656
kWh
$2,638
-
kW-mo/yr
$2,851
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs