| Assessment Year | 2005 |
|---|---|
| Principal Product | Architectural Flush Wood Doors |
| NAICS | 321911: Wood Window and Door Manufacturing |
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 193 |
| Plant Area |
146,000
ft2
|
| Annual Production | 350,000
ton
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $107,243 | 3,516,585 |
kWh
|
$0.030 |
| Electricity Demand | $125,331 | 9,816 |
kW-mo/yr
|
$12.77 |
| Electricity Fees | $12,362 | - |
|
- |
| Natural Gas | $182,659 | 24,617 |
MMBtu
|
$7.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $223,733 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,699 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $623 | $72 |
$360
12,480
kWh
|
$263
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,055 | $307 |
$1,189
41,230
kWh
|
$866
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,172 | $19,200 |
$4,720
163,904
kWh
|
$3,452
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.7135: Install occupancy sensors | $281 | $539 |
$281
9,735
kWh
|
- | - | - | - | |
| 05 | 4.111: Add equipment/ operators to reduce production bottleneck | $182,520 | $28,170 | - | - | - | - | $182,520 | |
| 06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $25,383 | $83,500 | - | - | - | $25,383 | - | |
| 07 | 3.4151: Minimize water usage | $4,699 | $20 | - | - |
$4,699
-
Tgal
|
- | - | |
| TOTAL RECOMMENDED | $223,733 | $131,808 |
$6,550
227,349
kWh
|
$4,581
-
kW-mo/yr
|
$4,699
-
Tgal
|
$25,383 | $182,520 | ||
| TOTAL IMPLEMENTED | $4,699 | $20 | - | - |
$4,699
-
Tgal
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Consumption Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs