Assessment Year | 1998 |
---|---|
Principal Product | liquid and bulk materials trailors |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 125 |
Plant Area |
250,000
ft2
|
Annual Production | 520
pieces
|
Production Hrs. Annual | 5,460
hrs
|
Location (State) | Kansas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $119,932 | 4,583,822 |
kWh
|
$0.026 |
Electricity Demand | $118,023 | 17,628 |
kW-mo/yr
|
$6.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $246,905 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,601 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,970 | $3,670 |
$932
35,756
kWh
|
$1,038
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,774 | $871 |
$1,293
49,531
kWh
|
$1,481
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7135: Install occupancy sensors | $530 | $399 |
$530
20,223
kWh
|
- | - | - | - | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $255 | $50 |
$30
1,172
kWh
|
$225
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $68,734 | $2,250 | - | - | - |
$321
-
lb
|
- | $68,413 | - | - | - | |
06 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $6,857 | $7,990 | - | - |
$4,943
-
lb
|
- | $(-396.0) | - | - | $2,310 | - | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $115,785 | $151,000 | - |
$137
-
kW-mo/yr
|
- | - | $32,448 | - | - | - | $83,200 | |
08 | 4.121: Maintain clean conditions before painting | $50,000 | $47,669 | - | - | - | - | - | - | $50,000 | - | - | |
TOTAL RECOMMENDED | $246,905 | $213,899 |
$2,785
106,682
kWh
|
$2,881
-
kW-mo/yr
|
$4,943
-
lb
|
$321
-
lb
|
$32,052 | $68,413 | $50,000 | $2,310 | $83,200 | ||
TOTAL IMPLEMENTED | $11,601 | $12,531 |
$2,225
85,287
kWh
|
$2,519
-
kW-mo/yr
|
$4,943
-
lb
|
- | $(-396.0) | - | - | $2,310 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs