Assessment Year | 1993 |
---|---|
Principal Product | aluminum and zinc castings |
NAICS |
n/a
|
SIC | 3363: Aluminum Die-Castings |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
100,000
ft2
|
Annual Production | 1,890,349
lb
|
Production Hrs. Annual | 6,120
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,359 | 5,890,094 |
kWh
|
$0.026 |
Natural Gas | $143,207 | 55,136 |
MMBtu
|
$2.60 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $29,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,886 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,690 | $660 |
$15,690
279,308
kWh
|
- | |
02 | 2.7241: Install outside air damper / economizer on hvac unit | $3,118 | $1,188 |
$3,118
55,393
kWh
|
- | |
03 | 2.7492: Use proper thickness of insulation on building envelope | $4,196 | $2,893 | - |
$4,196
-
MMBtu
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $3,763 | $714 |
$3,763
67,116
kWh
|
- | |
05 | 2.7135: Install occupancy sensors | $2,302 | $1,215 |
$2,302
41,032
kWh
|
- | |
TOTAL RECOMMENDED | $29,069 | $6,670 |
$24,873
442,849
kWh
|
$4,196
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,886 | $3,553 |
$15,690
279,308
kWh
|
$4,196
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs