ITAC Assessment: GT0973
ITAC logo
ITAC Assessment: GT0973
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Printing Inks and Coatings
NAICS 325910: Printing Ink Manufacturing
SIC 2893: Printing Ink
Sales Range $10
M
to 50
M
# of Employees 22
Plant Area 52,500
ft2
Annual Production 10,661,211
lb
Production Hrs. Annual 2,500
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $76,827 481,200
kWh
Natural Gas $46,628 3,422
MMBtu
TOTAL YEARLY COSTS $123,455
RECOMMENDED SAVINGS* $63,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,930

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $7,645 $800 - $7,645 - -
02 2.6211: Conserve energy by efficient use of vending machines $394 $90 $394
2,465
kWh
- - -
03 2.8123: Pay utility bills on time $689 $200 - $689 - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $305 $200 $305
1,906
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,586 $1,850 $4,486
28,035
kWh
- - $(-2,900.0)
06 2.9114: Use solar heat to make electricty $25,481 $338,242 $25,481
159,597
kWh
- - -
07 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $27,850 $175,000 $40,000
250,000
kWh
- $(-12,150.0)
-
MMBtu
-
TOTAL RECOMMENDED $63,950 $516,382 $70,666
442,003
kWh
$8,334 $(-12,150.0)
-
MMBtu
$(-2,900.0)
TOTAL IMPLEMENTED $9,930 $2,940 $5,185
32,406
kWh
$7,645 - $(-2,900.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs