ITAC Assessment: GT0963
ITAC logo
ITAC Assessment: GT0963
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Plastic Sheeting
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 77,000
ft2
Annual Production 330,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $535,303 5,512,827
kWh
Natural Gas $6,911 675
MMBtu
TOTAL YEARLY COSTS $542,214
RECOMMENDED SAVINGS* $88,267 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $20,364

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Personnel Changes Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $19,639 $1,850 $22,539
232,365
kWh
$(-2,900.0) -
02 2.3132: Recharge batteries on during off-peak demand periods $2,457 $400 - - $2,457
03 2.7224: Reduce space conditioning during non-working hours $725 $450 $725
7,477
kWh
- -
04 2.7135: Install occupancy sensors $1,308 $1,330 $1,308
13,484
kWh
- -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $7,066 $11,282 $7,066
72,846
kWh
- -
06 2.9114: Use solar heat to make electricty $57,072 $862,249 $57,072
587,758
kWh
- -
TOTAL RECOMMENDED $88,267 $877,561 $88,710
913,930
kWh
$(-2,900.0) $2,457
TOTAL IMPLEMENTED $20,364 $2,300 $23,264
239,842
kWh
$(-2,900.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs