| Assessment Year | 2023 |
|---|---|
| Principal Product | Plastic Sheeting |
| NAICS | 326199: All Other Plastics Product Manufacturing |
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 95 |
| Plant Area |
77,000
ft2
|
| Annual Production | 330,000
units
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $535,303 | 5,512,827 |
kWh
|
$0.097 |
| Natural Gas | $6,911 | 675 |
MMBtu
|
$10.24 |
| TOTAL YEARLY COSTS | $542,214 | |||
| RECOMMENDED SAVINGS* | $88,267 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $20,364 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,639 | $1,850 |
$22,539
232,365
kWh
|
$(-2,900.0) | - | |
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $2,457 | $400 | - | - | $2,457 | |
| 03 | 2.7224: Reduce space conditioning during non-working hours | $725 | $450 |
$725
7,477
kWh
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $1,308 | $1,330 |
$1,308
13,484
kWh
|
- | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,066 | $11,282 |
$7,066
72,846
kWh
|
- | - | |
| 06 | 2.9114: Use solar heat to make electricty | $57,072 | $862,249 |
$57,072
587,758
kWh
|
- | - | |
| TOTAL RECOMMENDED | $88,267 | $877,561 |
$88,710
913,930
kWh
|
$(-2,900.0) | $2,457 | ||
| TOTAL IMPLEMENTED | $20,364 | $2,300 |
$23,264
239,842
kWh
|
$(-2,900.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs