Assessment Year | 2003 |
---|---|
Principal Product | AUTO PISTONS |
NAICS | 336310: Motor Vehicle Gasoline Engine and Engine Parts Manufacturing |
SIC | 3592: Carburetors, Pistons, Piston Rings, and Valves |
Sales Range | $10 M to 50M |
# of Employees | 252 |
Plant Area |
105,000
ft2
|
Annual Production | 7,500,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $759,889 | 23,678,400 |
kWh
|
$0.032 |
Electricity Demand | $246,989 | 42,871 |
kW-mo/yr
|
$5.76 |
Natural Gas | $113,555 | 13,500 |
MMBtu
|
$8.41 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $126,987 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $37,310 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8112: Combine utility meters | $3,600 | - | - | - | $3,600 | |
02 | 2.2691: Shut off cooling if cold outside air will cool process | $17,568 | $23,870 |
$11,881
352,516
kWh
|
$5,687
-
kW-mo/yr
|
- | |
03 | 2.2691: Shut off cooling if cold outside air will cool process | $882 | $650 |
$189
5,987
kWh
|
$693
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,260 | $1,050 |
$12,325
365,671
kWh
|
$2,935
-
kW-mo/yr
|
- | |
05 | 2.4322: Use or replace with energy efficient substitutes | $28,826 | $1,248 |
$23,284
739,200
kWh
|
$5,542
-
kW-mo/yr
|
- | |
06 | 2.2514: Cover open tanks | $3,255 | $3,703 |
$2,628
77,960
kWh
|
$627
-
kW-mo/yr
|
- | |
07 | 2.2514: Cover open tanks | $2,447 | $3,500 |
$1,975
58,617
kWh
|
$472
-
kW-mo/yr
|
- | |
08 | 2.2514: Cover open tanks | $23,765 | $700 |
$19,184
569,168
kWh
|
$4,581
-
kW-mo/yr
|
- | |
09 | 2.2511: Insulate bare equipment | $29,561 | $12,093 |
$23,880
708,495
kWh
|
$5,681
-
kW-mo/yr
|
- | |
10 | 2.6218: Turn off equipment when not in use | $1,823 | - |
$1,823
54,078
kWh
|
- | - | |
TOTAL RECOMMENDED | $126,987 | $46,814 |
$97,169
2,931,692
kWh
|
$26,218
-
kW-mo/yr
|
$3,600 | ||
TOTAL IMPLEMENTED | $37,310 | $25,570 |
$24,395
724,174
kWh
|
$9,315
-
kW-mo/yr
|
$3,600 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs