Assessment Year | 2000 |
---|---|
Principal Product | Cargo Plane Parts |
NAICS |
n/a
|
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
101,075
ft2
|
Annual Production | 12
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,715 | 2,981,829 |
kWh
|
$0.028 |
Electricity Demand | $103,300 | 6,508 |
kW-mo/yr
|
$15.87 |
Electricity Fees | $12,000 | - |
|
- |
Natural Gas | $19,492 | 2,524 |
MMBtu
|
$7.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $186,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $88,180 | $220,000 | n/a |
$12,979
370,750
kWh
|
$97,060
-
kW-mo/yr
|
- | - |
$(-16,296.0)
-
MMBtu
|
- | $(-5,563.0) | - |
02 | 2.8113: Purchase gas directly from a contract gas supplier | $3,484 | - | n/a | - | - | - | - | - | - | - | $3,484 |
03 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $37,040 | $10,000 | n/a | - | - | - | - | - |
$13,335
-
lb
|
- | $23,705 |
04 | 2.7132: Install timers on light switches in little used areas | $3,123 | $400 | n/a |
$1,692
52,755
kWh
|
$1,254
-
kW-mo/yr
|
$177 | - | - | - | - | - |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,706 | $22,711 | n/a |
$4,314
134,818
kWh
|
$4,726
-
kW-mo/yr
|
$666 | - | - | - | - | - |
06 | 2.7226: Use computer programs to optimize hvac performance | $45,013 | $120,000 | n/a |
$39,965
1,253,810
kWh
|
- | $2,650 |
$2,398
-
MMBtu
|
- | - | - | - |
TOTAL RECOMMENDED | $186,546 | $373,111 |
$58,950
1,812,133
kWh
|
$103,040
-
kW-mo/yr
|
$3,493 |
$2,398
-
MMBtu
|
$(-16,296.0)
-
MMBtu
|
$13,335
-
lb
|
$(-5,563.0) | $27,189 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs