ITAC Assessment: GT0649
ITAC logo
ITAC Assessment: GT0649
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Carpet Backing
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 36
Plant Area 59,000
ft2
Annual Production 45,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,284 2,303,927
kWh
Electricity Demand $29,088 6,060
kW-mo/yr
Electricity Fees $6,529 -
Natural Gas $251,019 53,490
MMBtu
LPG $5,254 539
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $371,288 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
01 2.8113: Purchase gas directly from a contract gas supplier $66,324 $81,400 - - - - - - $66,324 -
02 2.8112: Combine utility meters $2,240 - - - - - - - $2,240 -
03 2.2511: Insulate bare equipment $1,648 $1,050 $916
48,359
kWh
$639
-
kW-mo/yr
$93 - - - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,426 $150 $896
47,479
kWh
$449
-
kW-mo/yr
$81 - - - - -
05 2.4133: Use most efficient type of electric motors $1,544 $17,439 $980
51,583
kWh
$518
-
kW-mo/yr
$46 - - - - -
06 4.114: Add/modify equipment to improve drying process $289,504 $27,000 $4,596
230,363
kWh
- - $25,086
-
MMBtu
- $259,200 - $622
-
Tgal
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,456 $6,189 $912
48,066
kWh
$461
-
kW-mo/yr
$83 - - - - -
08 3.4111: Use closed cycle process to minimize waste water production $3,046 - $(-1,425.0)
(-75,029)
kWh
$(-720.0)
-
kW-mo/yr
$(-129.0) - - - - $5,320
-
Tgal
09 3.1291: Eliminate practice of mixing waste streams $4,100 $1,000 - - - - $4,100
-
gal
- - -
TOTAL RECOMMENDED $371,288 $134,228 $6,875
350,821
kWh
$1,347
-
kW-mo/yr
$174 $25,086
-
MMBtu
$4,100
-
gal
$259,200 $68,564 $5,942
-
Tgal
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs