Assessment Year | 1998 |
---|---|
Principal Product | Carpet Backing |
NAICS |
n/a
|
SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 36 |
Plant Area |
59,000
ft2
|
Annual Production | 45,000
thousand feet
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $48,284 | 2,303,927 |
kWh
|
$0.021 |
Electricity Demand | $29,088 | 6,060 |
kW-mo/yr
|
$4.80 |
Electricity Fees | $6,529 | - |
|
- |
Natural Gas | $251,019 | 53,490 |
MMBtu
|
$4.69 |
LPG | $5,254 | 539 |
MMBtu
|
$9.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $371,288 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8113: Purchase gas directly from a contract gas supplier | $66,324 | $81,400 | - | - | - | - | - | - | $66,324 | - | |
02 | 2.8112: Combine utility meters | $2,240 | - | - | - | - | - | - | - | $2,240 | - | |
03 | 2.2511: Insulate bare equipment | $1,648 | $1,050 |
$916
48,359
kWh
|
$639
-
kW-mo/yr
|
$93 | - | - | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,426 | $150 |
$896
47,479
kWh
|
$449
-
kW-mo/yr
|
$81 | - | - | - | - | - | |
05 | 2.4133: Use most efficient type of electric motors | $1,544 | $17,439 |
$980
51,583
kWh
|
$518
-
kW-mo/yr
|
$46 | - | - | - | - | - | |
06 | 4.114: Add/modify equipment to improve drying process | $289,504 | $27,000 |
$4,596
230,363
kWh
|
- | - |
$25,086
-
MMBtu
|
- | $259,200 | - |
$622
-
Tgal
|
|
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,456 | $6,189 |
$912
48,066
kWh
|
$461
-
kW-mo/yr
|
$83 | - | - | - | - | - | |
08 | 3.4111: Use closed cycle process to minimize waste water production | $3,046 | - |
$(-1,425.0)
(-75,029)
kWh
|
$(-720.0)
-
kW-mo/yr
|
$(-129.0) | - | - | - | - |
$5,320
-
Tgal
|
|
09 | 3.1291: Eliminate practice of mixing waste streams | $4,100 | $1,000 | - | - | - | - |
$4,100
-
gal
|
- | - | - | |
TOTAL RECOMMENDED | $371,288 | $134,228 |
$6,875
350,821
kWh
|
$1,347
-
kW-mo/yr
|
$174 |
$25,086
-
MMBtu
|
$4,100
-
gal
|
$259,200 | $68,564 |
$5,942
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs