Assessment Year | 1997 |
---|---|
Principal Product | Joint Compound |
NAICS |
n/a
|
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 67 |
Plant Area |
70,000
ft2
|
Annual Production | 261,000,000
lb
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $66,057 | 2,859,613 |
kWh
|
$0.023 |
Electricity Demand | $95,062 | 5,966 |
kW-mo/yr
|
$15.93 |
Electricity Fees | $10,133 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $281,772 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $13,133 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $564 | $4,997 |
$172
7,327
kWh
|
$365
-
kW-mo/yr
|
$27 | - | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,920 | $2,120 |
$552
24,033
kWh
|
$1,277
-
kW-mo/yr
|
$91 | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,899 | $450 |
$2,112
91,442
kWh
|
$2,554
-
kW-mo/yr
|
$233 | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,314 | $7,680 |
$2,364
102,286
kWh
|
$3,649
-
kW-mo/yr
|
$301 | - | - | - | |
05 | 4.211: Consider use / purchase of bulk materials where possible | $139,500 | $155,000 | - | - | - |
$700
-
lb
|
- | $138,800 | |
06 | 3.7212: Improved material handling (mixing and transfer) | $3,175 | $2,800 | - | - | - | - | - | $3,175 | |
07 | 4.441: Install automatic packing equipment | $125,400 | $150,000 | - | - | - | - | $125,400 | - | |
TOTAL RECOMMENDED | $281,772 | $323,047 |
$5,200
225,088
kWh
|
$7,845
-
kW-mo/yr
|
$652 |
$700
-
lb
|
$125,400 | $141,975 | ||
TOTAL IMPLEMENTED | $13,133 | $10,250 |
$5,028
217,761
kWh
|
$7,480
-
kW-mo/yr
|
$625 | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs