| Assessment Year | 1994 |
|---|---|
| Principal Product | Polypropylene Carpet Yarn |
| NAICS |
n/a
|
| SIC | 2281: Yarn Spinning Mills |
| Sales Range | $1 M to 5M |
| # of Employees | 99 |
| Plant Area |
64,000
ft2
|
| Annual Production | 113,400
thousand feet
|
| Production Hrs. Annual | 8,664
hrs
|
| Location (State) | Georgia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $653,536 | 9,648,007 |
kWh
|
$0.068 |
| Natural Gas | $56,224 | 13,927 |
MMBtu
|
$4.04 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $42,220 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $32,800 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,060 | $21,660 |
$10,060
148,593
kWh
|
- | - | |
| 02 | 2.7122: Disconnect ballasts | $360 | $640 |
$360
5,275
kWh
|
- | - | |
| 03 | 2.4133: Use most efficient type of electric motors | $9,620 | $17,130 |
$9,620
142,145
kWh
|
- | - | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $580 | $1,920 |
$580
8,499
kWh
|
- | - | |
| 05 | 2.2612: Use cooling tower water instead of refrigeration | $6,070 | $4,600 | - | - |
$6,070
-
Tgal
|
|
| 06 | 2.2163: Use minimum steam operating pressure | $200 | - | - |
$200
-
MMBtu
|
- | |
| 07 | 2.2414: Use waste heat from hot flue gases to preheat | $2,770 | $13,000 | - |
$2,770
-
MMBtu
|
- | |
| 08 | 2.2136: Install / repair insulation on steam lines | $890 | $900 | - |
$890
-
MMBtu
|
- | |
| 09 | 2.2135: Repair and eliminate steam leaks | $11,670 | $700 | - |
$11,670
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $42,220 | $60,550 |
$20,620
304,512
kWh
|
$15,530
-
MMBtu
|
$6,070
-
Tgal
|
||
| TOTAL IMPLEMENTED | $32,800 | $41,030 |
$20,040
296,013
kWh
|
$12,760
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs