ITAC Assessment: GT0516
ITAC logo
ITAC Assessment: GT0516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1993
Principal Product Glass Containers
NAICS
n/a
SIC 3221: Glass Containers
Sales Range $10
M
to 50
M
# of Employees 625
Plant Area
n/a
Annual Production 1,460,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $4,027,326 96,014,363
kWh
Natural Gas $4,605,600 1,976,570
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $135,620 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $3,280 - $3,280
78,253
kWh
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $21,340 $72,000 $21,340
509,086
kWh
-
03 2.2223: Enhance sensitivity of temperature control and cutoff $72,000 $40,000 - $72,000
-
MMBtu
04 2.4314: Use synthetic lubricant $39,000 - $39,000
932,005
kWh
-
TOTAL RECOMMENDED $135,620 $112,000 $63,620
1,519,344
kWh
$72,000
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs