ITAC Assessment: GT0392
ITAC logo
ITAC Assessment: GT0392
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product PROCESSED CHICKEN
NAICS
n/a
SIC 2015: Poultry Slaughtering and Processing
Sales Range $10
M
to 50
M
# of Employees 525
Plant Area
n/a
Annual Production 75,000,000
lb
Production Hrs. Annual 4,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $518,951 9,553,927
kWh
LPG $11,056 1,832
MMBtu
Fuel Oil #2 $101,533 24,780
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $107,838 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $82,128

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $1,550 - - $2,150
-
MMBtu
$(-600.0)
02 2.4133: Use most efficient type of electric motors $1,803 $2,217 $1,803
32,532
kWh
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,625 - $1,625
29,894
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $650 - $650
12,016
kWh
- -
05 2.2136: Install / repair insulation on steam lines $3,680 $2,110 - $3,680
-
MMBtu
-
06 2.2135: Repair and eliminate steam leaks $3,490 $375 - $3,490
-
MMBtu
-
07 2.7142: Utilize higher efficiency lamps and/or ballasts $4,120 $1,220 $4,120
75,909
kWh
- -
08 2.2515: Use optimum thickness insulation $14,830 $22,000 $14,830
273,154
kWh
- -
09 2.4323: Use optimum size and capacity equipment $41,430 $16,000 $41,430
762,896
kWh
- -
10 2.2437: Recover waste heat from equipment $9,490 $27,500 - $9,490
-
MMBtu
-
11 2.2515: Use optimum thickness insulation $740 $1,190 $740
13,482
kWh
- -
12 3.7214: Reduce or eliminate waste $24,430 - - - $24,430
TOTAL RECOMMENDED $107,838 $72,612 $65,198
1,199,883
kWh
$18,810
-
MMBtu
$23,830
TOTAL IMPLEMENTED $82,128 $21,922 $48,978
901,231
kWh
$9,320
-
MMBtu
$23,830
Yearly Savings* Imp'd Cost* Electricity Usage Savings Fuel Oil #2 Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs