Assessment Year | 1989 |
---|---|
Principal Product | PROCESSED CHICKEN |
NAICS |
n/a
|
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | $10 M to 50M |
# of Employees | 525 |
Plant Area |
n/a
|
Annual Production | 75,000,000
lb
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $518,951 | 9,553,927 |
kWh
|
$0.054 |
LPG | $11,056 | 1,832 |
MMBtu
|
$6.03 |
Fuel Oil #2 | $101,533 | 24,780 |
MMBtu
|
$4.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $107,838 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $82,128 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,550 | - | - |
$2,150
-
MMBtu
|
$(-600.0) | |
02 | 2.4133: Use most efficient type of electric motors | $1,803 | $2,217 |
$1,803
32,532
kWh
|
- | - | |
03 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,625 | - |
$1,625
29,894
kWh
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $650 | - |
$650
12,016
kWh
|
- | - | |
05 | 2.2136: Install / repair insulation on steam lines | $3,680 | $2,110 | - |
$3,680
-
MMBtu
|
- | |
06 | 2.2135: Repair and eliminate steam leaks | $3,490 | $375 | - |
$3,490
-
MMBtu
|
- | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,120 | $1,220 |
$4,120
75,909
kWh
|
- | - | |
08 | 2.2515: Use optimum thickness insulation | $14,830 | $22,000 |
$14,830
273,154
kWh
|
- | - | |
09 | 2.4323: Use optimum size and capacity equipment | $41,430 | $16,000 |
$41,430
762,896
kWh
|
- | - | |
10 | 2.2437: Recover waste heat from equipment | $9,490 | $27,500 | - |
$9,490
-
MMBtu
|
- | |
11 | 2.2515: Use optimum thickness insulation | $740 | $1,190 |
$740
13,482
kWh
|
- | - | |
12 | 3.7214: Reduce or eliminate waste | $24,430 | - | - | - | $24,430 | |
TOTAL RECOMMENDED | $107,838 | $72,612 |
$65,198
1,199,883
kWh
|
$18,810
-
MMBtu
|
$23,830 | ||
TOTAL IMPLEMENTED | $82,128 | $21,922 |
$48,978
901,231
kWh
|
$9,320
-
MMBtu
|
$23,830 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs