ITAC Assessment: GT0130
ITAC logo
ITAC Assessment: GT0130
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product LUMBER
NAICS
n/a
SIC 2421: Sawmills and Planing Mills, General
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area
n/a
Annual Production 25,000
thousand feet
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $144,942 3,108,734
kWh
Natural Gas $232,971 54,424
MMBtu
Fuel Oil #2 $54,064 7,020
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $288,008 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $288,008

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 3.6123: Burn wood by-products for heat $287,035 $250,000 - $232,971
-
MMBtu
$54,064
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $322 $600 $322
7,034
kWh
- -
03 2.4133: Use most efficient type of electric motors $651 $3,569 $651
14,068
kWh
- -
TOTAL RECOMMENDED $288,008 $254,169 $973
21,102
kWh
$232,971
-
MMBtu
$54,064
-
MMBtu
TOTAL IMPLEMENTED $288,008 $254,169 $973
21,102
kWh
$232,971
-
MMBtu
$54,064
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs