| Assessment Year | 1999 |
|---|---|
| Principal Product | Industrial Floor Cleaning Machines |
| NAICS |
n/a
|
| SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 450 |
| Plant Area |
500,000
ft2
|
| Annual Production | 52,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Minnesota |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $223,230 | 6,661,489 |
kWh
|
$0.034 |
| Electricity Demand | $118,284 | 15,108 |
kW-mo/yr
|
$7.83 |
| Electricity Fees | $3,490 | - |
|
- |
| Natural Gas | $142,217 | 33,727 |
MMBtu
|
$4.22 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $289,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $14,686 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,686 | $60,411 |
$10,176
299,531
kWh
|
$4,510
-
kW-mo/yr
|
- | - | |
| 02 | 2.2511: Insulate bare equipment | $189 | $1,008 | - | - |
$189
-
MMBtu
|
- | |
| 03 | 2.2314: Replace heat treating oven with more efficient unit | $274,833 | $125,000 | - | - |
$25,233
-
MMBtu
|
$249,600 | |
| TOTAL RECOMMENDED | $289,708 | $186,419 |
$10,176
299,531
kWh
|
$4,510
-
kW-mo/yr
|
$25,422
-
MMBtu
|
$249,600 | ||
| TOTAL IMPLEMENTED | $14,686 | $60,411 |
$10,176
299,531
kWh
|
$4,510
-
kW-mo/yr
|
- | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs