ITAC Assessment: CO0660
ITAC logo
ITAC Assessment: CO0660
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Cellulose insulation
NAICS 322299: All Other Converted Paper Product Manufacturing
SIC 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 7
Plant Area 9,600
ft2
Annual Production 12,000
ton
Production Hrs. Annual 2,340
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $17,998 337,800
kWh
Electricity Demand $73,158 3,622
kW-mo/yr
Electricity Fees $1,462 -
LPG $1,795 54
MMBtu
Fuel Oil #2 $6,149 261
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,530 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,120

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $510 $3,090 $190
3,000
kWh
$320
-
kW-mo/yr
-
02 2.8121: Apply for tax-free status for energy purchases $2,610 $500 - - $2,610
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,410 $3,310 $520
8,200
kWh
$890
-
kW-mo/yr
-
TOTAL RECOMMENDED $4,530 $6,900 $710
11,200
kWh
$1,210
-
kW-mo/yr
$2,610
TOTAL IMPLEMENTED $3,120 $3,590 $190
3,000
kWh
$320
-
kW-mo/yr
$2,610
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs