Assessment Year | 2006 |
---|---|
Principal Product | Chocolate candy |
NAICS | 311352: Confectionery Manufacturing from Purchased Chocolate |
SIC | 2064: Candy and Other Confectionery Products |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
56,000
ft2
|
Annual Production | 300,000
lb
|
Production Hrs. Annual | 2,516
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $95,216 | 1,793,600 |
kWh
|
$0.053 |
Electricity Demand | $46,282 | 3,984 |
kW-mo/yr
|
$11.62 |
Natural Gas | $83,864 | 8,027 |
MMBtu
|
$10.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $11,602 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,152 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $242 | $462 |
$155
2,864
kWh
|
$87
-
kW-mo/yr
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $910 | $270 |
$540
10,000
kWh
|
$370
-
kW-mo/yr
|
- | - | - | |
03 | 2.2136: Install / repair insulation on steam lines | $180 | $80 | - | - |
$180
-
MMBtu
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,310 | $21,480 |
$3,340
61,900
kWh
|
$1,880
-
kW-mo/yr
|
- | $40 | $50 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,310 | $6,180 |
$2,450
45,300
kWh
|
$720
-
kW-mo/yr
|
- | $80 | $60 | |
06 | 2.9114: Use solar heat to make electricty | $1,650 | $2,950 |
$920
17,000
kWh
|
$730
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $11,602 | $31,422 |
$7,405
137,064
kWh
|
$3,787
-
kW-mo/yr
|
$180
-
MMBtu
|
$120 | $110 | ||
TOTAL IMPLEMENTED | $1,152 | $732 |
$695
12,864
kWh
|
$457
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs