ITAC Assessment: CO0592
ITAC logo
ITAC Assessment: CO0592
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Chocolate candy
NAICS 311352: Confectionery Manufacturing from Purchased Chocolate
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 70
Plant Area 56,000
ft2
Annual Production 300,000
lb
Production Hrs. Annual 2,516
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,216 1,793,600
kWh
Electricity Demand $46,282 3,984
kW-mo/yr
Natural Gas $83,864 8,027
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,602 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,152

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $242 $462 $155
2,864
kWh
$87
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $910 $270 $540
10,000
kWh
$370
-
kW-mo/yr
- - -
03 2.2136: Install / repair insulation on steam lines $180 $80 - - $180
-
MMBtu
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $5,310 $21,480 $3,340
61,900
kWh
$1,880
-
kW-mo/yr
- $40 $50
05 2.7142: Utilize higher efficiency lamps and/or ballasts $3,310 $6,180 $2,450
45,300
kWh
$720
-
kW-mo/yr
- $80 $60
06 2.9114: Use solar heat to make electricty $1,650 $2,950 $920
17,000
kWh
$730
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $11,602 $31,422 $7,405
137,064
kWh
$3,787
-
kW-mo/yr
$180
-
MMBtu
$120 $110
TOTAL IMPLEMENTED $1,152 $732 $695
12,864
kWh
$457
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs