Assessment Year | 2004 |
---|---|
Principal Product | Contract fabricated metal parts |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
103,100
ft2
|
Annual Production | 200
pieces
|
Production Hrs. Annual | 5,096
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,752 | 1,970,185 |
kWh
|
$0.027 |
Electricity Demand | $74,260 | 5,599 |
kW-mo/yr
|
$13.26 |
Electricity Fees | $1,500 | - |
|
- |
Natural Gas | $58,915 | 9,694 |
MMBtu
|
$6.08 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $22,280 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $8,330 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $4,630 | $1,790 | - | - |
$4,630
-
MMBtu
|
|
02 | 2.4239: Eliminate or reduce compressed air usage | $3,590 | $4,680 |
$1,830
69,400
kWh
|
$1,760
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,360 | $570 |
$1,200
45,600
kWh
|
$1,160
-
kW-mo/yr
|
- | |
04 | 2.2514: Cover open tanks | $1,200 | $750 |
$710
26,800
kWh
|
$490
-
kW-mo/yr
|
- | |
05 | 2.4239: Eliminate or reduce compressed air usage | $880 | $240 |
$550
20,900
kWh
|
$330
-
kW-mo/yr
|
- | |
06 | 2.2711: Utilize outside air instead of conditioned air for drying | $300 | $420 |
$150
5,700
kWh
|
$150
-
kW-mo/yr
|
- | |
07 | 2.7243: Improve air circulation with destratification fans / other methods | $9,320 | $27,720 |
$(-580.0)
(-22,100)
kWh
|
$(-400.0)
-
kW-mo/yr
|
$10,300
-
MMBtu
|
|
TOTAL RECOMMENDED | $22,280 | $36,170 |
$3,860
146,300
kWh
|
$3,490
-
kW-mo/yr
|
$14,930
-
MMBtu
|
||
TOTAL IMPLEMENTED | $8,330 | $6,660 |
$4,440
168,400
kWh
|
$3,890
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs