| Assessment Year | 2001 |
|---|---|
| Principal Product | Napkins,bathroom tissue and paper bags |
| NAICS |
n/a
|
| SIC | 2674: Uncoated Paper and Multiwall Bags |
| Sales Range | $50 M to 100M |
| # of Employees | 150 |
| Plant Area |
253,700
ft2
|
| Annual Production | 24,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | New Mexico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $233,639 | 5,372,000 |
kWh
|
$0.043 |
| Electricity Demand | $40,015 | 853 |
kW-mo/yr
|
$46.91 |
| Electricity Fees | $82,321 | - |
|
- |
| Natural Gas | $29,828 | 3,785 |
MMBtu
|
$7.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $98,780 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $82,560 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $20,780 | $61,010 |
$12,950
228,300
kWh
|
$7,830
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $10,820 | $4,110 | - | - |
$10,820
-
MMBtu
|
- | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,740 | $570 |
$4,470
113,100
kWh
|
$2,050
-
kW-mo/yr
|
- | $(-780.0) | - | - | |
| 04 | 2.4238: Do not use compressed air for personal cooling | $3,630 | $1,000 |
$2,050
51,900
kWh
|
$1,580
-
kW-mo/yr
|
- | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $1,870 | $1,300 |
$1,240
31,300
kWh
|
$630
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,550 | - |
$2,590
65,500
kWh
|
$1,270
-
kW-mo/yr
|
- | $(-520.0) | $(-1,790.0) | - | |
| 07 | 2.7135: Install occupancy sensors | $220 | $210 |
$150
3,700
kWh
|
$70
-
kW-mo/yr
|
- | - | - | - | |
| 08 | 4.651: Install back-up equipment | $54,170 | $84,380 | - | - | - | - | - | $54,170 | |
| TOTAL RECOMMENDED | $98,780 | $152,580 |
$23,450
493,800
kWh
|
$13,430
-
kW-mo/yr
|
$10,820
-
MMBtu
|
$(-1,300.0) | $(-1,790.0) | $54,170 | ||
| TOTAL IMPLEMENTED | $82,560 | $147,260 |
$18,660
372,700
kWh
|
$10,510
-
kW-mo/yr
|
- | $(-780.0) | - | $54,170 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs