Assessment Year | 2001 |
---|---|
Principal Product | beer |
NAICS |
n/a
|
SIC | 2082: Malt Beverages |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
18,500
ft2
|
Annual Production | 620,000
Tgal
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $5,105 | 310,724 |
kWh
|
$0.016 |
Electricity Demand | $11,906 | 1,693 |
kW-mo/yr
|
$7.03 |
Electricity Fees | $507 | - |
|
- |
Natural Gas | $19,879 | 3,420 |
MMBtu
|
$5.81 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,490 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,060 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,160 | - | - |
$1,160
-
kW-mo/yr
|
- | - | - | - | - | |
02 | 2.3191: Use demand controller or load shedder | $500 | $1,000 | - |
$500
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $90 | - |
$50
2,800
kWh
|
$100
-
kW-mo/yr
|
- | - | $(-50.0) | $(-10.0) | - | |
04 | 3.4114: Replace city water with recycled water via cooling tower | $4,810 | $4,730 | - | - |
$2,870
-
Tgal
|
- | - | - |
$1,940
-
Tgal
|
|
05 | 3.5317: Sell / offer by-product as animal feed | $1,930 | $1,930 | - | - | - |
$1,930
-
gal
|
- | - | - | |
TOTAL RECOMMENDED | $8,490 | $7,660 |
$50
2,800
kWh
|
$1,760
-
kW-mo/yr
|
$2,870
-
Tgal
|
$1,930
-
gal
|
$(-50.0) | $(-10.0) |
$1,940
-
Tgal
|
||
TOTAL IMPLEMENTED | $6,060 | $4,730 |
$50
2,800
kWh
|
$1,260
-
kW-mo/yr
|
$2,870
-
Tgal
|
- | $(-50.0) | $(-10.0) |
$1,940
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs