ITAC Assessment: CO0483
ITAC logo
ITAC Assessment: CO0483
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product beer
NAICS
n/a
SIC 2082: Malt Beverages
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 18,500
ft2
Annual Production 620,000
Tgal
Production Hrs. Annual 4,160
hrs
Location (State) Colorado

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $5,105 310,724
kWh
Electricity Demand $11,906 1,693
kW-mo/yr
Electricity Fees $507 -
Natural Gas $19,879 3,420
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,490 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,060

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Other Liquid (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Water Consumption Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,160 - - $1,160
-
kW-mo/yr
- - - - -
02 2.3191: Use demand controller or load shedder $500 $1,000 - $500
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $90 - $50
2,800
kWh
$100
-
kW-mo/yr
- - $(-50.0) $(-10.0) -
04 3.4114: Replace city water with recycled water via cooling tower $4,810 $4,730 - - $2,870
-
Tgal
- - - $1,940
-
Tgal
05 3.5317: Sell / offer by-product as animal feed $1,930 $1,930 - - - $1,930
-
gal
- - -
TOTAL RECOMMENDED $8,490 $7,660 $50
2,800
kWh
$1,760
-
kW-mo/yr
$2,870
-
Tgal
$1,930
-
gal
$(-50.0) $(-10.0) $1,940
-
Tgal
TOTAL IMPLEMENTED $6,060 $4,730 $50
2,800
kWh
$1,260
-
kW-mo/yr
$2,870
-
Tgal
- $(-50.0) $(-10.0) $1,940
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs