| Assessment Year | 2000 |
|---|---|
| Principal Product | hydraulic fluid control valves |
| NAICS |
n/a
|
| SIC | 3492: Fluid Power Valves and Hose Fittings |
| Sales Range | $1 M to 5M |
| # of Employees | 140 |
| Plant Area |
62,500
ft2
|
| Annual Production | 10,000
pieces
|
| Production Hrs. Annual | 4,108
hrs
|
| Location (State) | Colorado |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $61,067 | 2,084,701 |
kWh
|
$0.029 |
| Electricity Demand | $65,793 | 5,590 |
kW-mo/yr
|
$11.77 |
| Electricity Fees | $3,137 | - |
|
- |
| Natural Gas | $27,773 | 4,343 |
MMBtu
|
$6.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,340 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,120 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,380 | $7,500 | - |
$6,380
-
kW-mo/yr
|
- | - | - | - | |
| 02 | 2.7135: Install occupancy sensors | $1,340 | $2,850 |
$570
24,033
kWh
|
$770
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $660 | - |
$380
17,878
kWh
|
$1,120
-
kW-mo/yr
|
- | - | $(-240.0) | $(-600.0) | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $660 | $1,000 |
$570
33,411
kWh
|
- | - | - | - | $90 | |
| 05 | 3.3122: Use filtration, centrifuging to remove contaminants | $1,880 | - | - | - |
$50
-
gal
|
- | $360 | $1,470 | |
| 06 | 3.6192: Use a less expensive method of waste removal | $320 | - | - | - | - |
$360
-
lb
|
- | $(-40.0) | |
| 07 | 4.621: Use fixtures to reduce machine changeout times | $5,100 | $1,510 | - | - | - | - | $5,100 | - | |
| TOTAL RECOMMENDED | $16,340 | $12,860 |
$1,520
75,322
kWh
|
$8,270
-
kW-mo/yr
|
$50
-
gal
|
$360
-
lb
|
$5,220 | $920 | ||
| TOTAL IMPLEMENTED | $13,120 | $10,010 |
$950
51,289
kWh
|
$7,500
-
kW-mo/yr
|
- |
$360
-
lb
|
$4,860 | $(-550.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Solid Waste (haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs