ITAC Assessment: CL1801
ITAC logo
ITAC Assessment: CL1801
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Shock Absorbers
NAICS 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $100
M
to 500
M
# of Employees 600
Plant Area 400,000
ft2
Annual Production 7,500,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,571,566 25,204,206
kWh
Electricity Demand $17,263 2,877
kW-mo/yr
Natural Gas $486,187 114,226
MMBtu
Waste Disposal Costs
Water Usage $163,048 69,004,200
Tgal
TOTAL YEARLY COSTS $2,238,064
RECOMMENDED SAVINGS* $166,921 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $68,074 $111,703 $59,744
957,442
kWh
$8,330
-
kW-mo/yr
- -
02 2.2421: Install waste heat boiler to provide direct power $47,531 $15,500 - - $47,531
-
MMBtu
-
03 3.4159: Replace treated water with well / surface water $25,853 $4,700 - - - $25,853
-
Tgal
04 2.1221: Replace obsolete burners with more efficient ones $13,900 $22,500 - - $13,900
-
MMBtu
-
05 2.4111: Utilize energy-efficient belts and other improved mechanisms $9,775 $4,800 $8,637
138,408
kWh
$1,138
-
kW-mo/yr
- -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,788 $2,080 $1,580
25,316
kWh
$208
-
kW-mo/yr
- -
TOTAL RECOMMENDED $166,921 $161,283 $69,961
1,121,166
kWh
$9,676
-
kW-mo/yr
$61,431
-
MMBtu
$25,853
-
Tgal
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs