Assessment Year | 2017 |
---|---|
Principal Product | Greige textile products |
NAICS | 314999: All Other Miscellaneous Textile Product Mills |
SIC | 2399: Fabricated Textile Products, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 413 |
Plant Area |
620,332
ft2
|
Annual Production | 19,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | South Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,399,039 | 46,548,000 |
kWh
|
$0.052 | |
Electricity Demand | $105,043 | 7,758 |
kW-mo/yr
|
$13.54 | |
Natural Gas | $293,332 | 67,158 |
MMBtu
|
$4.37 | |
Waste Disposal Costs | |||||
Water Usage | $159,292 | 38,700 |
Tgal
|
$4.12 | |
TOTAL YEARLY COSTS | $2,956,706 | ||||
RECOMMENDED SAVINGS* | $261,908 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2421: Install waste heat boiler to provide direct power | $148,148 | $211,152 | - | - |
$148,148
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $95,734 | $244,620 |
$62,951
1,210,588
kWh
|
$32,783
-
kW-mo/yr
|
- | - | |
03 | 3.4156: Use flow control valves on equipment to optimize water use | $15,929 | $3,050 | - | - | - |
$15,929
-
Tgal
|
|
04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $2,097 | $900 |
$1,379
26,520
kWh
|
$718
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $261,908 | $459,722 |
$64,330
1,237,108
kWh
|
$33,501
-
kW-mo/yr
|
$148,148
-
MMBtu
|
$15,929
-
Tgal
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs