ITAC Assessment: CI0075
ITAC logo
ITAC Assessment: CI0075
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Crumb Rubber
NAICS 326299: All Other Rubber Product Manufacturing
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 33
Plant Area 65,000
ft2
Annual Production 52,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $413,649 3,633,521
kWh
Electricity Demand $323,711 9,444
kW-mo/yr
Electricity Fees $94,711 -
Natural Gas $51,183 3,897
MMBtu
LPG $26,000 1,186
MMBtu
Other Gas $8,573 1
MMBtu
TOTAL YEARLY COSTS $917,827
RECOMMENDED SAVINGS* $197,655 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.2515: Use optimum thickness insulation $55,664 $84,000 $55,664
489,136
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,877 $4,900 $21,956
192,934
kWh
$9,921
-
kW-mo/yr
-
03 2.2511: Insulate bare equipment $26,083 $1,476 $16,763
147,302
kWh
$9,320
-
kW-mo/yr
-
04 2.8227: Adjust / maintain fork lift trucks for most efficient operation $23,870 $108,000 $(-2,130.0)
(-18,720)
kWh
- $26,000
-
MMBtu
05 2.3141: Use battery storage for demand control $23,252 $100,000 $7,809
76,526
kWh
$15,443
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $15,578 $17,110 $10,371
91,136
kWh
$5,207
-
kW-mo/yr
-
07 2.9114: Use solar heat to make electricty $15,333 $89,460 $11,215
98,548
kWh
$4,118
-
kW-mo/yr
-
08 2.4239: Eliminate or reduce compressed air usage $3,438 $10,000 $3,438
30,213
kWh
- -
09 2.7135: Install occupancy sensors $2,560 $900 $1,573
13,824
kWh
$987
-
kW-mo/yr
-
TOTAL RECOMMENDED $197,655 $415,846 $126,659
1,120,899
kWh
$44,996
-
kW-mo/yr
$26,000
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs