ITAC Assessment: BD0202
ITAC logo
ITAC Assessment: BD0202
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Industrial Metal Fasteners
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 500,000
ft2
Annual Production 450,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $293,971 8,294,040
kWh
Electricity Demand $203,299 18,554
kW-mo/yr
Electricity Fees $360 -
Natural Gas $737,628 118,486
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $171,285 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7231: Use radiant heater for spot heating $90,110 $47,000 - - $90,110
-
MMBtu
- - - -
02 2.2426: Use waste heat from flue gases to heat space conditioning air $10,572 $25,000 - - $10,572
-
MMBtu
- - - -
03 2.1222: Install turbulators $7,093 $1,200 - - $7,093
-
MMBtu
- - - -
04 2.4314: Use synthetic lubricant $6,166 $3,000 $3,257
91,993
kWh
$2,909
-
kW-mo/yr
- - - - -
05 2.4133: Use most efficient type of electric motors $5,720 $14,230 $3,395
95,911
kWh
$2,325
-
kW-mo/yr
- - - - -
06 2.1213: Direct warmest air to combustion intake $4,357 $6,000 - - $4,357
-
MMBtu
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,945 $2,300 $1,028
29,079
kWh
$917
-
kW-mo/yr
- - - - -
08 2.7135: Install occupancy sensors $1,490 $1,350 $405
11,423
kWh
$1,085
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $1,068 $2,150 $518
14,640
kWh
$218
-
kW-mo/yr
- - - - $332
10 2.7142: Utilize higher efficiency lamps and/or ballasts $550 $540 $212
5,992
kWh
$90
-
kW-mo/yr
- - - - $248
11 3.3131: Use evaporation to concentrate material $27,967 $10,000 - - - - $27,967
-
gal
- -
12 3.4115: Recover and reuse cooling water $3,392 $12,000 - - - $3,392
-
Tgal
- - -
13 4.821: Pay bills on time to avoid late fees $10,555 - - - - - - $10,555 -
14 3.5316: Contract a wood pallet recycling company $300 $500 - - - - - - $300
TOTAL RECOMMENDED $171,285 $125,270 $8,815
249,038
kWh
$7,544
-
kW-mo/yr
$112,132
-
MMBtu
$3,392
-
Tgal
$27,967
-
gal
$10,555 $880
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs