ITAC Assessment: BD0139
ITAC logo
ITAC Assessment: BD0139
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Metal Fasteners
NAICS
n/a
SIC 3452: Bolts, Nuts, Screws, Rivets, and Washers
Sales Range $50
M
to 100
M
# of Employees 300
Plant Area 143,000
ft2
Annual Production 13,700,000
lb
Production Hrs. Annual 6,032
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $521,027 7,371,923
kWh
Electricity Demand $226,327 16,022
kW-mo/yr
Electricity Fees $1,934 -
Natural Gas $35,348 11,526
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,504 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,033

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings By-product Production Savings
01 2.4133: Use most efficient type of electric motors $15,947 $28,000 $10,395
261,723
kWh
$5,552
-
kW-mo/yr
- - - -
02 2.4314: Use synthetic lubricant $7,711 $2,400 $4,515
113,716
kWh
$3,196
-
kW-mo/yr
- - - -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,947 $4,800 $3,877
97,597
kWh
$2,070
-
kW-mo/yr
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,316 - $1,941
48,945
kWh
$1,375
-
kW-mo/yr
- - - -
05 2.1311: Replace electrically-operated equipment with fossil fuel equipment $2,135 $1,200 $2,013
50,996
kWh
$793
-
kW-mo/yr
$(-671.0)
-
MMBtu
- - -
06 2.7135: Install occupancy sensors $1,586 $750 $882
22,274
kWh
$704
-
kW-mo/yr
- - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $630 $545 $286
7,327
kWh
$344
-
kW-mo/yr
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $275 $410 $185
4,689
kWh
$90
-
kW-mo/yr
- - - -
09 3.5112: Reprocess spent oils on site for re-use $7,003 $5,500 - - - - $7,003
-
lb
-
10 3.4111: Use closed cycle process to minimize waste water production $3,154 $9,500 $(-397.0)
(-9,965)
kWh
$(-346.0)
-
kW-mo/yr
- $3,897
-
Tgal
- -
11 4.122: Develop standard procedures to improve internal yields $55,272 $5,000 - - - - $55,272
-
lb
-
12 4.131: Modify process to reduce material use/cost $528 $250 - - - - - $528
TOTAL RECOMMENDED $103,504 $58,355 $23,697
597,302
kWh
$13,778
-
kW-mo/yr
$(-671.0)
-
MMBtu
$3,897
-
Tgal
$62,275
-
lb
$528
TOTAL IMPLEMENTED $31,033 $40,855 $16,925
426,435
kWh
$10,211
-
kW-mo/yr
- $3,897
-
Tgal
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Solid Waste (non-haz) Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs