ITAC Assessment: BD0087
ITAC logo
ITAC Assessment: BD0087
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Steel Balls
NAICS
n/a
SIC 3315: Steel Wiredrawing and Steel Nails and Spikes
Sales Range $10
M
to 50
M
# of Employees 99
Plant Area 83,500
ft2
Annual Production 6,240
ton
Production Hrs. Annual 7,488
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,596 6,671,161
kWh
Electricity Demand $65,308 15,661
kW-mo/yr
Electricity Fees $9,998 -
Natural Gas $117,554 33,967
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $64,931 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $52,734

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.4133: Use most efficient type of electric motors $20,443 $40,890 $18,069
471,864
kWh
$2,374
-
kW-mo/yr
- - - -
02 2.1114: Limit and control secondary combustion air in furnace $7,026 $8,500 - - $7,026
-
MMBtu
- - -
03 2.7491: Insulate glazing, walls, ceilings, and roofs $5,680 $5,100 $2,445
65,358
kWh
- $3,235
-
MMBtu
- - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $5,171 $3,750 $7,313
47,773
kWh
$676
-
kW-mo/yr
$(-2,818.0)
-
MMBtu
- - -
05 2.7135: Install occupancy sensors $1,365 $1,125 $1,293
33,705
kWh
$72
-
kW-mo/yr
- - - -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $10,295 $7,000 $(-8.0)
(-293)
kWh
- - $(-1,290.0) $11,593 -
07 4.611: Begin a practice of predictive / preventative maintenance $14,951 $3,000 - - - - - $14,951
TOTAL RECOMMENDED $64,931 $69,365 $29,112
618,407
kWh
$3,122
-
kW-mo/yr
$7,443
-
MMBtu
$(-1,290.0) $11,593 $14,951
TOTAL IMPLEMENTED $52,734 $57,115 $21,799
570,634
kWh
$2,446
-
kW-mo/yr
$3,235
-
MMBtu
$(-1,290.0) $11,593 $14,951
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs