ITAC Assessment: BD0083
ITAC logo
ITAC Assessment: BD0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Precision Sheet Metal Parts
NAICS
n/a
SIC 3469: Metal Stampings, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 62
Plant Area 34,500
ft2
Annual Production 375
ton
Production Hrs. Annual 2,470
hrs
Location (State) Illinois

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,923 656,800
kWh
Electricity Demand $37,450 3,037
kW-mo/yr
Electricity Fees $1,311 -
Natural Gas $11,762 2,496
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,846 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,537

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings
01 2.7314: Reduce ventilation air $2,435 $4,400 $680
16,120
kWh
- $1,755
-
MMBtu
- - -
02 2.7491: Insulate glazing, walls, ceilings, and roofs $1,943 $1,860 $281
6,741
kWh
- $1,662
-
MMBtu
- - -
03 2.4133: Use most efficient type of electric motors $1,552 $2,800 $740
17,878
kWh
$812
-
kW-mo/yr
- - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,241 $450 $1,241
30,188
kWh
- - - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,122 $1,740 $485
11,723
kWh
$637
-
kW-mo/yr
- - - -
06 2.7491: Insulate glazing, walls, ceilings, and roofs $455 $529 $66
1,465
kWh
- $389
-
MMBtu
- - -
07 2.4314: Use synthetic lubricant $398 $175 $229
5,569
kWh
$169
-
kW-mo/yr
- - - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $348 - $348
8,499
kWh
- - - - -
09 3.4115: Recover and reuse cooling water $10,457 $10,250 $(-446.0)
(-10,844)
kWh
$(-550.0)
-
kW-mo/yr
- $11,453
-
Tgal
- -
10 3.1191: Change procedures / equipment / operating conditions $1,653 $750 - - - - - $1,653
11 3.4151: Minimize water usage $642 $875 - - - $642
-
Tgal
- -
12 4.126: Install sensors to detect defects $2,600 $725 - - - - $2,600 -
TOTAL RECOMMENDED $24,846 $24,554 $3,624
87,339
kWh
$1,068
-
kW-mo/yr
$3,806
-
MMBtu
$12,095
-
Tgal
$2,600 $1,653
TOTAL IMPLEMENTED $8,537 $6,539 $2,905
70,340
kWh
$981
-
kW-mo/yr
$2,051
-
MMBtu
- $2,600 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs